Typical Hardscape Project Process/Timeline

Initial call or email inquiry

Initial consult scheduled 1 to 2 weeks out depending on the time of year.

Initial consultation with designer

Usually approximately 30 minutes, but varies based on the project.

Designer prepares a drawing and proposal for installation

1 to 2 weeks after initial consultation depending on the time of year.

Revisions

Review designer drawings – depends on the project.

Contract is signed

Down payment is invoiced approximately 2 weeks prior to the start of work. – Schedule backlog varies depending on the time of year and other projects.

Project work commences

Project length varies.  Approximately 1 day per 100 square feet of paver patio installation, 1-2 days for steps (depending on how many), 2-3+ days for seat walls (depending on length/how many), 1+ days for landscape (depending on scope).